Witech Excavating was selected by ARCO/Murray to complete full site development for the 1,200,000-square-foot GBOGH industrial facility in Morris, Illinois. This 12-month project included implementation of the Storm Water Pollution Prevention Plan (SWPPP), tree clearing and grubbing, mass site excavation, fine grading, and aggregate placement for both slab-on-grade and concrete pavement areas. The scope also extended to grading for a new railroad spur and future development expansion.

In total, Witech moved over 530,000 cubic yards of earth and placed 65,000 tons of aggregate, delivering precise subgrade preparation and durable base materials that met strict industrial specifications. Leveraging GPS technology and experienced field supervision, our team ensured accuracy, efficiency, and a seamless coordination process from start to finish—culminating in another successful partnership with ARCO/Murray and a foundation ready for long-term performance.

The team’s precision-driven approach, led by General Superintendent Kyle Peel, ensured accurate grades, efficient scheduling, and seamless coordination with ARCO/Murray’s construction timeline. The result was a clean, well-balanced site and a stable foundation built to support a major industrial operation and future expansion.

Market
Industrial
Client
ARCO / Murray
Type of Project
Aggregate Placement, Grading, Mass Earthwork, Structure Excavation / Backfill
Scoped Performance
Over 530,000 cubic yards of earth were moved, including 242,000 CY of topsoil excavation, 269,000 CY of site cut to structural fill, and 26,000 CY of trade spoils to structural fill. Witech also performed 275,000 square yards of fine grading and placed 65,000 cubic yards of topsoil along with 65,000 tons of aggregate for slab-on-grade, pavement base, and railroad sub-ballast.
Duration
12 Months